Lots of progress with Walls & Roof…unfortunately a big dent in the balance sheet…HELP for funds required!! Posted on October 25, 2016 by goodwoodmasjid
Another Eid passed and tremendous progress by the construction team Posted on September 12, 2016 by goodwoodmasjid Scaffold ready for roof works Side Brickwork View
Amazing work over the last month…Floors all in for Ground, First & Second. Internal walls have started and even the roof works… Posted on August 23, 2016 by goodwoodmasjid
Happy Eid to all of you and look what was achieved this week!!! Posted on July 8, 2016July 8, 2016 by goodwoodmasjid
A few weeks delay as some bad weather…worst June for years!! However it’s all happening…Steel Supports are well on the way up Posted on July 5, 2016July 5, 2016 by goodwoodmasjid
The Final Foundation….concrete to be filled if it does not rain today!! Then 23 Steel Supports will be to be fitted in about 2 weeks time!! Posted on June 14, 2016 by goodwoodmasjid
Everyone happy for work to resume. Some of the foundations now ready with concreting taking place!! Posted on May 26, 2016 by goodwoodmasjid